First, the use of lifting devices

Lifting devices are also called "reverse joints" and "breakout devices." It is an important part of a small rotary drilling rig and is used to lift drill rods and drilling tools.

Second, the structure and performance of the inducer

The upper end is connected with the main winch wire rope of the small rotary drilling rig, and the lower end is connected with the drill rod. With the retraction of the main hoisting wire rope, the rotary drill pipe and the drill bit are driven to increase and lower, and the drill bit is rotated when the power head is rotated. When drilling and dumping soil, it assumes the changing force of the drill rod, and through its own rotation, it removes the change of the transmission force of the steel wire rope due to the rotation of the drill rod and the like, and avoids the situation that the steel wire rope presents kinks, warping, cracking, etc., and then brings the situation. Come to the big deal. Therefore, the lifting device should have a satisfactory tensile strength and a sensitive rotation capability under a large pulling force.

Third, the use of induction agent matters needing attention

1. Before using the inducer, or for a long period of time, the small rotary drilling rig should be filled with grease. After the injection, the joint is rolled to ensure that it can roll without sticking.

2. Grease unscrew and remove the oil plug, oil (grease gun, etc.) Slowly inject grease into the grease nipple until it is jointed from the lower end of the lower part and tighten the screw plug. Overflow, foreign matter enters the oil passage.

3. At both ends of the pin end, the lifter and the lifter, place the U-shaped groove joint in the lug hole of the drill pipe, penetrate the lower pin shaft installation, flat washer, spring coil and stop pin; the main winding wire rope loop U-grooves, holes, and pins, flat washers, spring rings, and pins.

4. Before installing the drill pipe, it must be ensured that the U-shaped groove of the joint under the traction device is straight and the ground so that the guide can move up and down along the straight line and the ground. Slowly increase the main hoist until the drill pipe is installed.

IV. Routine maintenance and protection of inducers

1. Before replacing the old and new grease until the new grease overflows, each shift (approx. 12 hours) must apply lubricant to the lubrication device to ensure good lubrication and rotation. Rotate the joint by hand to see if the roll has stagnated.

2, check the oil spilled oil, such as oil has been mixed with foreign particles such as sand, mud, said the existing seal must provide damage, the need for timely replacement or repair, can not continue to use.

3. Check whether the appearance of the elevator is not damaged, whether the pin connections at both ends are reliable, and whether there is abnormal leakage of grease.

4, according to the different time, replace the different traces of grease, if not long-term use, please fill the small rotary drilling rig with grease. (This article comes from Jiangsu Taixin)

Related news: Taixin rotary drilling rig maintenance

Emulsion Hydraulic Motor

Emulsion Hydraulic Motor,Hydraulic Drive Motor,Hydro Motor,Hydraulic Pump Motor

Ningbo delambo hydraulic power Co.,LTD , https://www.sun-seiko-hyd.com